Estimates: ROM vs Definitive for PMP Exam
In project cost and time management, estimations are often used in arriving at the cost and time at various stage along the project management cycle as the accurate cost and time will not be 100% known until the very end of the project. In estimating the cost and time, there are two important estimate metrics: Rough Order of Magnitude (ROM) Estimate vs Definitive Estimate (note: the degree of accuracy of the estimates must be clearly stated in the documents).
This post will expound on the similarities and differences of ROM Estimate vs Definitive and what Aspirants would need to know for the exam.
Article Highlights
ROM Estimate vs Definitive Estimate
- Rough Order of Magnitude (ROM) Estimate: the differences between estimates and actual figures may be as large as 75% more or 25% less
- used in early stage of the project when things are not very solid/clear and/or for projects that span a lengthy period
- Definitive Estimate: the differences between estimates and actual figures may be within the range of -5% to + 10% (more or less)
- used in latter stage of the project and/or the project is simple to estimate
In addition to the ROM Estimate and Definitive Estimate, there are some more estimation ranges:
- Preliminary estimate: within the range of -15% to +50%
- Budget estimate: within the range of -10% to +25%
- Final estimate: 100% accurate
The degree of accuracy of the estimations will become more accurate as the project proceed as many unknowns at the beginning of the project will become known later on.
ROM Estimate vs Definitive Estimate Illustrated
Let’s take the project of PMP Exam study and preparation again for the illustration of the degree of accuracy of estimation.
At the very beginning of the exam preparation, the Aspirants may have little or no previous knowledge about the exam syllabus and the PMBOK® Guide. The actual period of time required for the studies may not be known accurately. The only way to estimate the study period is through the lessons learned of other exam takers.
And as a rule of thumb, the estimated preparation period for the exam is roughly 3 months of part-time study, which is considered a Rough Order of Magnitude (ROM) Estimate.
But after going through the exam prep course, the PMP Aspirant will then be able to understand the topics for the exam and their knowledge gaps. Hence a more accurate estimate can be made (e.g. 100 days — more like a Definitive Estimate). And at that time, it is often advisable to book the exact date of the exam, which can also act as a driving force for the PMP study.
Mock Exam Question
- The project is working into 3/4 of project duration and the final component is to be built to improve the accuracy of the system. The project manager is updating the cost of the whole system. What is the degree of accuracy of the estimate?
- Preliminary Estimate
- Rough Order of Magnitude Estimate
- Budget Estimate
- Definitive Estimate
Solution: D
Since it is near the end of the development of the system, most of the costs of the system have already been known. The only variable is that “final component”. It could be inferred that the cost estimate for the whole system at this point should be well within -5% to +10% (i.e. Definitive Estimate)
Conclusion: ROM Estimate vs Definitive Estimate
The various degree of accuracy of estimations mentioned in the PMBOK® Guide and other PMP Exam Prep books are listed below:
- Rough Order of Magnitude (ROM) Estimate: within the range of -25% to +75%
- Preliminary estimate: within the range of -15% to +50%
- Budget estimate: within the range of -10% to +25%
- Definitive Estimate: within the range of -5% to +10%
- Final estimate: 100% accurate
Hope this article can illustrate the differences between ROM Estimate vs Definitive Estimate well.
Most Popular PMP Certification Exam Articles
- My Exam Prep Tips and Free Resources (I got 4P and 1 MP)
- How to Get 35 Contact Hours Fast and Easy?
- Detailed Comparision of online PMP Courses
- Over 1000+ FREE Quality Mock Exam / Practice Questions
- A FREE Guide to Formulas and Calculation (with explanation and sample questions)
- 47 Commonly Confused Terms with detailed explanation
Hi,
This was quite helpful but the content is overlapped on right pane of the screen which makes us difficult to read the entire text. It would be great if that is fixed..
Thanks
M.Ce
Sorry about that, should be fixed now…
Hi
Please I need past questions for my PMP preparation. How can you help me?
Hi ik,
You may refer to this page for some quality sample PMP Exam questions:
https://edward-designer.com/web/list-of-free-pmp-exam-questions/
Wish you PMP success!
Hi Edward,
The definitions are very useful for exam preparation. one advice is in the starting the Definitive Estimate is within the range of -5% to +10%, but in the exam answer it’s mentioned as Definitive Estimate: within the range of +5% to -10%.
Please check once.
Thanks,
Naresh
My bad, thanks for pointing that out!
Hi Edward,
Your blog is a really awesome & very useful resource of information and its really helping me in my PMP exam preps.
I’ve question about the above article which is as follow,
You have mentioned two ranges for “Definitive Estimate”, a) -5% to +10% and b) -10% to +10%. if both of these ranges are right, then which one to chose for the answer on exam.
Also, in PMBOK 5th Edition Pg. 201, only one range is mentioned for Definitive Estimate which is -5% to +10%. So how come there are two ranges?
Sorry for my typo. The range for Definitive Estimate for the PMP Exam should be -5% to +10%.(the PMBOK Guide is the ultimate answer).
Remarks: in reality, this range for Definitive Estimate would differ according to usage. Different sources would quote -10% to +10%. It is recommended to have a clear definition for your projects.
Hi Edward,
Your blog is awesome ! It has really helped me to prepare. I want to bring to your notice a possible typo for % of ROM. As per Rita ROM value is -25% to +75%. Can you please double check on values you have listed in your blog ( -50% to +50%)
Thanks for the correction. I have just updated the blog!
Hi Chi Wing,
My name is Chi Pan and I am thankful that I found your website. I was thinking of PMP Exam a couple of months ago and got side-tracked. You may say “procrastination”. So I am now ready (maybe not 100% :)). Do you think taking a two-week break for family vacation in End of July would ruin my study stream for PMP Exam, which I am thinking of taking it in September of 2017 as you had suggested after coming back from vacation? Hope you can give me some suggestions. Thanks for all the tips.
Chi
Hi Chi Pan,
A break with family will certainly not stand in the way of your PMP Exam prep. Instead, this would give you the much needed relaxation and your mind will be fully refreshed after the vacation. My family is my source of strength! Do play hard and study hard! Wish you PMP success!