PRINCE2 Foundation Certification Notes 9: Change Theme


PRINCE2 Foundation Certification Notes 9: Change Theme

Important: The new PRINCE2® Foundation and Practitioner exams (PRINCE2® 2017) are available from 10 July 2017 (details of the changes here). Don’t worry, the changes are quite minor indeed as all the 7 principles, themes and processes remain the same. From now on until the end of 2017, candidates can take either the existing or updated English versions of the PRINCE2® exam. All PRINCE2® Foundation and Practitioner exams will be based on PRINCE2® 2017 from 1 January 2018. You can still seize the time to get certified based on the current version! Once you get PRINCE2® certified, your certification is still valid under PRINCE2® 2017 and onwards!

Introduction: In PRINCE2®, there are 7 Themes describing important aspects of project management that are vital to the success of the project. The Change Theme is the sixth PRINCE2® Theme which provides an approach to identify, assess and control any potential changes to the project (as changes are inevitable) to increase the likelihood of project success. The PRINCE2® Foundation Study Notes for the Change Theme below details what are needed for the PRINCE2® Foundation Exam.

PRINCE2® Theme: Change

  • The Change Theme is to provide a mechanism for Issues and Change Control during the life of the project to ensure changes to the baseline are approved and recorded.
  • The Issue and Change Management approach is formulated during the Initiation Stage and can be reviewed in the Managing a Stage Boundary process at stage ends.
  • Configuration Management is a key process for Change Control which is a systematic approach to the creation, maintenance and controlled change of the configuration of a product (called “configuration item”) so that the correct version/state of the product are used/delivered.

Key Definitions

  • Baseline: (a.k.a. first agreed version) once the product is approved by the relevant management levels, it is considered “baselined”
  • Release: a set of managed and approved products handed over to users.
  • Change Authority: a group of persons responsible for considering change requests and off-specifications (the project board or can be assigned to others)
  • Change Budget: the fund set aside for change requests (including analysis) which can only be authorized by the Change Authority
  • Issue: any events not planned in the project, including 3 types:
    • Request for Change: a proposal for a change to a baseline (e.g. the Product Description document), need approval from Change Authority
    • Off-Specification: agreed to be done but is not provided (e.g. a missing product), need Change Authority for direction
    • Problem/Concern: (may be positive or negative) other issues the Project Manager need to handle (if within the tolerance) or escalate (e.g. to be handled with an Exception Plan)

PRINCE2® Approach to Change

  • There are 6 PRINCE2® management products for change and issue control:
    • Configuration Management Strategy — documents the strategy on issue and change management
    • Configuration Items Records — contains the details of each configuration items in the project
    • Product Status Account — a report of the status of (all/selected) products
    • Daily Log — used by the Project Manager for all informal information (note: formal information to be put in the Issue/Risk Register)
    • Issue Register — captures and maintains issues
    • Issue Reports — describes issues in detail
  • Issue Prioritization and Rating
    • Prioritization with MoSCoW
      • Must have — essential for project objectives
      • Should have — would weaken the Business Case
      • Could have — nice to have
      • Won’t have (for now)
    • Rating with Severity
      • can be a scale or 1-5 or word descriptions (e.g. critical/major/significant/normal/minor)

Configuration Management Procedure

  1. Planning — decide which documents/products need to be controlled (usually depending on the scale of the project)
  2. Identification — decide the coding system for each configuration item
  3. Control — controlling change activities: baselining, archiving, access control, distribution of copies
  4. Status Accounting — check and report a group of products
  5. Verification & Audit — verify that the Configuration Item Records are correct

Issue and Change Control Procedure

  1. Capture — type of issue (requests for change, off-specification or concerns/problems), initial analysis and whether they are formal or informal; an Issue Report would be created
  2. Examine — the impact of issue against project objectives in the aspects of business, user and supplier
  3. Propose — options, evaluate them and recommend the best action
  4. Decide — whether to accept the recommended solution by change authority / escalation needed in the form of Issue Report/Exception Report
  5. Implement — the corrective action

Change Theme: Roles and Responsibilities

  • Corporate or Programme Management: provide the Corporate policy and direction
  • Executive: determine Change Authority and Change Budget and determine the Configuration Management Strategy (e.g. severity/priority rating)
  • Senior Supplier(s): advise Project Manager for change requests
  • Project Manager: manage the Configuration Management procedure and Issues and Change control procedure; create and update the Issue Register
  • Project Assurance: check whether the Configuration Management Strategy is followed and provide advices
  • Team Manager: implements approved corrective actions
  • Project Support: updates the Configuration Items Records

(The PRINCE2® Change Theme is similar to the Project Integration Management (Perform Integrated Change Control) as described in the PMBOK® Guide for PMP Certification Exam dealing with tracking, controlling, approving, handling and archiving of all change requests in the project as in the PMP Exam.)

Wish you PRINCE2® Foundation Exam success!

 

Support website running for FREE, thanks!

If you find this post helpful and if you are thinking of buying from Amazon, please support the running cost of this website at no extra cost to you by searching and buying through the search box below. Thank you very much for your help!

Edward Chung

Edward Chung aspires to become a full-stack web developer and project manager. In the quest to become a more competent professional, Edward studied for and passed the PMP Certification, ITIL v3 Foundation Certification, PMI-ACP Certification and Zend PHP Certification. Edward shares his certification experience and resources here in the hope of helping others who are pursuing these certification exams to achieve exam success.

You may also like...

Leave a Reply

Your email address will not be published. Required fields are marked *