Project Risk Management: Avoid vs Mitigate for PMP Exam


Project Risk Management: Avoid vs Mitigate for PMP Exam

UPDATED for new PMP® Exam 2019.

In project risk management, there are several risk management strategies as recommended in the PMBOK® Guide for positive or negative risks:

  • For negative risks:
    • Mitigate
    • Avoid
    • Transfer
    • Accept
    • Escalate
  • For positive risks (i.e. opportunities):
    • Enhance
    • Exploit
    • Share
    • Accept

Out of the five risk management strategies for negative risks, “avoid” and “mitigate” are always not thoroughly understood and may be easily confused. Both “avoid” and “mitigate” aims at preventing the risks from occurring, yet there is one crucial different between these two risk management strategies. This post will expound on the similarities and differences of Avoid vs Mitigate and what Aspirants would need to know for the exam.

PMP® Definitions: Avoid vs Mitigate for PMP® Exam

  • Avoid: taking any possible measures/actions (e.g. changing the project plan or approach) to completely prevent the risks from occurring/eliminate the adverse effects once they occur
    • not many risks may be avoided (not realistic for most cases)
    • avoid usually involves a lot of costs
  • Mitigate: taking measures/actions (e.g. changing the project plan or approach) to reduce the likelihood of the risks from occurring/minimize the impact once they occur
    • some residual risks may remain

In addition, there are three more negative risk management strategies as outlined in the PMBOK® Guide:

  • Transfer: the negative impacts related to the occurrence of the risk are shifted to a 3rd party
    • the 3rd party will absorb all the losses
    • may be arranged in the form of insurance policy or penalty clause
    • usually involve contractual arrangements and considerations
  • Accept: the negative risks are to be accepted passively
    • no active actions / measures are carried out to reduce the likelihood of occurrence / degree of negative impact which might be caused by the occurrence of the risk
    • workarounds may be carried out as a response once the risks occur
  • Escalate: escalate the project risk to the appropriate party to handle it
    • no longer a responsibility of the project manager
    • can be deleted from the risk register or leave it there with a remark

Avoid vs Mitigate for PMP® Exam Illustrated

Let’s take the project of PMP® Exam study and preparation again for the illustration of the meanings of Avoid vs Mitigate risk management strategies.

One of the most common problem any PMP® Aspirant may face is to be late for the PMP® Exam owing to traffic jam (which you may just be denied the exam or have the exam time cut).  There are a number of suggestions for this risk as proposed by other Aspirants. We will look into the risk response strategies for the “Avoid” and “Mitigate” categories:

  • Avoid Risk Management Strategy
    • Do not take the PMP® Exam at all (avoid the Exam)
    • Walk to the PMP® Exam Centre instead of riding a car/bus/train (avoid any traffic)
    • Sleep at the door of the PMP® Exam centre the night before
  • Mitigate Risk Management Strategy
    • Go to the Exam centre at least 1 hours earlier than the Exam time in preparation of any traffic jam
    • Live in a hotel adjacent to the Exam centre to minimize the traffic time
    • Book an Exam centre in an area with little traffic jams
    • Book the PMP® Exam in the afternoon away from the morning peak hours

The “Do not take the PMP® Exam at all (avoid the Exam)” is certainly not a choice for most Aspirants. For the other strategies, additional costs from the risk budget may need to be spent. Some, e.g. booking a hotel room, is more expensive than the others.

PMP® Mock Exam Question

  1. David, the project manager, is currently in the “plan risk response” process. For the risk of summer typhoon which may adversely affect the building schedule of the factory, David plans to reschedule the beginning of construction in early winter. Which risk response is David adopting?
    1. Avoid
    2. Mitigate
    3. Accept
    4. Enhance
    Solution: A
    David makes use of the “Avoid” strategy to shift the construction time to early winter as typhoons normally come in summer and early autumn. There is no way to reduce the likelihood of the occurrence of typhoons so “Mitigate” is not the answer.

Conclusion: Avoid vs Mitigate for PMP® Exam

To distinguish between Avoid vs Mitigate, remember that:

  • Avoid: to completely eliminate the likelihood / impact of the risks
  • Mitigate: to reduce the impacts / the likelihood of occurrence of the risks

Hope this article can illustrate the differences between Avoid vs Mitigate for Aspirants well.

recommended PMP resourcesAdditional FREE PMP® resources: 47+ Commonly Confused Term Pairs with detailed explanations. If you found this article useful, you may wish to reference other Commonly Confused Term articles.

Most Popular PMP Certification Exam Articles

GreyCampus PMP online training course bundle for US$149 only

Support website running for FREE, thanks!

If you find this post helpful and if you are thinking of buying from Amazon, please support the running cost of this website at no extra cost to you by searching and buying through the search box below. Thank you very much for your help!

Edward Chung

Edward Chung aspires to become a full-stack web developer and project manager. In the quest to become a more competent professional, Edward studied for and passed the PMP Certification, ITIL v3 Foundation Certification, PMI-ACP Certification and Zend PHP Certification. Edward shares his certification experience and resources here in the hope of helping others who are pursuing these certification exams to achieve exam success.

You may also like...

Leave a Reply

Your email address will not be published. Required fields are marked *

2 Responses

  1. Joni says:

    for phrase: ‘Avoid: to complete eliminate the likelihood / impact of the risks’ consider changing from complete to completely