Resource Leveling vs Resource Smoothing for PMP Exam


Resource Leveling vs Resource Smoothing for PMP Exam

In the Project Schedule Management knowledge area of the PMP Exam syllabus, Resource Leveling and Resource Smoothing are two of the most important Resource Optimization Techniques for project schedule development to allow most effective allocation of resources to allow the project to be completed as fast as possible. However, given the two techniques look very similar on the surface, many Aspirants would misunderstand them and fail to employ the best technique according to the situation described in the PMP Exam questions.

Article Highlights

Resource Leveling and Resource Smoothing

During “Develop Project Schedule”, activities are usually first sequenced and assigned resources based on the dependencies between different activities (either mandatory/discretionary dependencies) without consideration of the loading of different activities. Thus, some resources may be over-loaded. In order to solve this issue, Resource Optimization Techniques are employed.

  • Resource Leveling: Resource Leveling is a resource optimization technique in which the Project Manager adjusts the start dates and finish dates of different activities in order to balance the demand for resources vs available supply.
    • Resource Leveling is always carried out first
    • e.g. Under normal situation, it is generally considered the man hour for each team member is 45 hours per week, if more than 45 hours’ work is assigned to a member in a particular week (which is not practical nor recommended by PMI), the activities must be adjusted by resource leveling and trimmed down to 45 hours — i.e. it takes more days to complete the activities than originally planned
  • Resource Smoothing: Resource Smoothing is a resource optimization technique in which the Project Manager adjusts the timing of different activities so that the requirement for resources does not exceed a certain pre-defined limit.
    • The pre-defined limit may be statutory or a company policy, e.g. no more than 38 hours’ work in a week
    • After Resource Leveling, Resource Smoothing is used to ensure the demand for a particular resource is more balanced over time — i.e. if the original plan requires the resources to work 45 hours during the first 3 weeks but only 20 hours for the next 2 weeks, resource smoothing will try to “smooth” the hours per week to around 35 for the 5 weeks of the project duration
    • While carrying out resource smoothing, care has to be taken to balance between the desire pre-defined limit and the overall duration of the project/activities. In this regards, the desired pre-defined limits may not always be possible.

Illustrated Example

For an aspirant named David, as he is having a full-time job, the maximum number of hours that can be devoted to exam prep is 20 hours per week. However, he prefers to work 10 hours per week in order to spare some time for his family.

As David wants to apply for the exam as soon as possible, he hope to finish his online course and get the 35 Contact Hours Certificate within two week. However, since it is estimated to take around 50 hours to be able to complete the online course and finish the final exam. The original plan is NOT feasible as he can only afford 20 hours per week. David has to employ Resource Leveling to extend the schedule to 2.5 weeks.

Summary

The end goal for the Resource Optimization Techniques:

  • If it is for meeting resource constraints (e.g. statutory requirements, resource availability), Resource Leveling is employed. Resource Leveling is a necessary as the original plan is not practical and feasible.
  • If it is for better utilization of resources or achieving the desired level of efforts (e.g. 38 hours per week to allow for some buffers of resources), Resource Smoothing is employed. Resource Smoothing is preferred but not absolutely necessary.

Resource leveling is always applied first before applying resource smoothing.

recommended PMP resourcesAdditional FREE PMP resources: 47+ Commonly Confused Term Pairs with detailed explanations. If you found this article useful, you may wish to reference other Commonly Confused Term articles.

Most Popular PMP Certification Exam Articles

Support website running for FREE, thanks!

If you find this post helpful and if you are thinking of buying from Amazon, please support the running cost of this website at no extra cost to you by searching and buying through the search box below. Thank you very much for your help!

Edward Chung

Edward Chung aspires to become a full-stack web developer and project manager. In the quest to become a more competent professional, Edward studied for and passed the PMP Certification, ITIL v3 Foundation Certification, PMI-ACP Certification and Zend PHP Certification. Edward shares his certification experience and resources here in the hope of helping others who are pursuing these certification exams to achieve exam success.

You may also like...

Leave a Reply

Your email address will not be published. Required fields are marked *

7 Responses

  1. Mohammed Aiman says:

    Resource Leveling can cause the projects’ critical path to change,
    while Resource Smoothing doesn’t alter the project’s critical path.

  2. Alexander says:

    It seems to me that the Resource Smoothing description here contradicts to what Rita Mulhacy says: “Resource smoothing is a modified form of resource leveling, where resources are leveled only within the limits of the float, so the completion dates are not delayed’.

    So, in the example above, David prefers to work less and lengthen the PMP prep to 3.33 weeks, meaning that the completion date is delayed. The example doesn’t imply that he has any positive float, so resource smoothing seems impossible.

    If my logic is correct, then I don’t understand why you would want to do Resource Levelling first, and Resource Smoothing afterward, and not vice versa. Shouldn’t you first look to level within the floats, and only if that’s impossible, do the Resource Levelling and affect the critical path?

    Please help me figure this out. Thank you!

  3. Yang says:

    I think this explanation is different from what is described in PMBOK 6th edition: the primary difference of these two resource optimization technique is whether the critical path can be changed.

  4. Chayanika says:

    You first say “Resource Leveling is always carried out first”. Then during the end of the article you say “Resource leveling is alwasy applied after applying resource smoothing.”. Is this correct? Also the spelling of always needs to be corrected.

    • Thanks Chayanika for pointing out the typo which has been amended immediately! To make it clear: Resource Leveling is always carried out first.

      Wish you PMP success!